Sustainable Northern Connectivity Strategy

Thompson, Manitoba

completeBroadband And ConnectivityMRIF
Federal contribution
$1.4M
$1,362,692
Federal share19%

of $7.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2005
2006200820102012
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 12, 2005(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction end4.5 years lateforecast Oct 1, 2007