Back to projects

City of Thompson Water and Waste Water Main Renewal

Thompson, Manitoba

underwayDrinking WaterGIS
Federal contribution
$18.8M
$18,804,500
Federal share40%

of $47.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
today
2022202420262028
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
City of Thompson
Construction start
Aug 3, 2022(actual)
Construction end
Oct 31, 2027(forecast)

Against the original forecast

  • Construction start14 months lateforecast Jun 15, 2021

Also in Thompson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58408 in the federal list. How to read these figures.