City of Thompson New Aquatic Facility
Federal contribution
$6.0M
$6,000,000
Federal share40%
of $15.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 9, 2022
today
2023202420252026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Thompson
- Construction start
- May 4, 2024(actual)
- Construction end
- Aug 30, 2026(forecast)