City of Thompson Wastewater Treatment Plant
Federal contribution
$12.1M
$12,103,008
Federal share33%
of $36.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 15, 2015
2016201820202022
Built
Approved 3 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Thompson
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Dec 16, 2022(actual)
Against the original forecast
- Construction end3 years lateforecast Nov 30, 2019
Also in Thompson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45684 in the federal list. How to read these figures.