Thompson Regional Community Complex
Federal contribution
$2.9M
$2,914,200
Federal share33%
of $8.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Thompson
- Construction start
- Mar 1, 2011(actual)
- Construction end
- May 7, 2012(actual)
Against the original forecast
- Construction end7 months earlyforecast Nov 30, 2012
Also in Thompson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25079 in the federal list. How to read these figures.