Schedule
Announced and approvedMar 14, 2007
2007200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Dauphin
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Jul 19, 2010(actual)
Against the original forecast
- Construction start4.2 years lateforecast Apr 15, 2005
- Construction end19 months lateforecast Dec 31, 2008