Back to projects

City of Dauphin Lagoon Expansion and Upgrade

Dauphin, Manitoba

underwayWastewaterGIS
Federal contribution
$5.0M
$4,983,200
Federal share40%

of $12.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2022
today
20232024202520262027
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Dauphin
Construction start
Nov 1, 2024(actual)
Construction end
Nov 30, 2026(forecast)