Dauphin Vermillion Park Rehabilitation and Redevelopment
Federal contribution
$166,667
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Dauphin
- Construction start
- Jul 15, 2012(actual)
- Construction end
- Feb 5, 2015(actual)
Against the original forecast
- Construction end15 months lateforecast Oct 31, 2013
Also in Dauphin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25312 in the federal list. How to read these figures.