Rural Water Pipelines
Federal contribution
$1.0M
$1,043,000
Federal share33%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Dauphin
- Construction start
- Jul 7, 2016(actual)
- Construction end
- Apr 27, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 20, 2016
- Construction end3 months lateforecast Jan 27, 2017
Also in Dauphin
- City of Dauphin Lagoon Expansion and Upgrade$5.0M
- Rural Waterline Expansion: Phase II$1.8M
- Water Distribution, Sewage Collection, Road Infrastructure & Fire Suppression Access Point Renewal$635.1K
- Dauphin Vermillion Park Rehabilitation and Redevelopment$166.7K
- Dauphin Arena Eco-Chill System Expansion$130.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46327 in the federal list. How to read these figures.