Road Construction

Kipling, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$34,842
Federal share25%

of $139.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
20062007
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 31, 2005(actual)
Construction end
Dec 31, 2006(actual)

Against the original forecast

  • Construction start8 months earlyforecast Apr 1, 2006
  • Construction end3 months earlyforecast Mar 31, 2007

Also in Kipling

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12715 in the federal list. How to read these figures.