Town of Kipling - Arena Upgrades
Federal contribution
$166,400
Federal share40%
of $416.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2022
2023
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Kipling
- Construction start
- Mar 1, 2023(actual)
- Construction end
- Oct 1, 2023(actual)