Water Treatment Plant Upgrades
Federal contribution
$2.2M
$2,162,780
Federal share50%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
2017201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Kipling
- Construction start
- Jul 27, 2018(actual)
- Construction end
- Mar 30, 2020(actual)
Against the original forecast
- Construction start15 months lateforecast May 1, 2017
Also in Kipling
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48460 in the federal list. How to read these figures.