Back to projects

Water Treatment Plant Upgrades

Kipling, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$2.2M
$2,162,780
Federal share50%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
2017201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Kipling
Construction start
Jul 27, 2018(actual)
Construction end
Mar 30, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast May 1, 2017

Also in Kipling

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48460 in the federal list. How to read these figures.