Sewage Lagoon Expansion

Kipling, Saskatchewan

completeWastewaterCC
Federal contribution
$188,822
Federal share33%

of $566.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Kipling
Construction start
Nov 30, 2010(actual)
Construction end
Oct 30, 2012(actual)

Against the original forecast

  • Construction start17 months lateforecast Jun 22, 2009