Watermain Replacement

Humboldt, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$144,188
Federal share25%

of $576.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2006
2006200720082009
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Humboldt
Construction start
Oct 31, 2005(actual)
Construction end
Feb 12, 2009(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Mar 31, 2009