West St. Paul Multiplex

West St. Paul, Manitoba

completeRecreationMRIF
Federal contribution
$257,716
Federal share15%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
2007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Feb 13, 2007(actual)
Construction end
Mar 30, 2010(actual)

Against the original forecast

  • Construction start15 months lateforecast Nov 1, 2005
  • Construction end15 months lateforecast Dec 31, 2008