RM of West St. Paul/RM of St. Andrews Regional Wastewater Collection System
Federal contribution
$4.0M
$4,000,000
Federal share33%
of $12.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2013201420152016
Built
Approved 3.2 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of West St. Paul
- Construction start
- Nov 4, 2013(actual)
- Construction end
- Jan 8, 2016(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 1, 2013
- Construction end3 months lateforecast Sep 30, 2015