Water Supply
Federal contribution
$2.7M
$2,665,635
Federal share44%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of West St. Paul
- Construction start
- Mar 6, 2017(actual)
- Construction end
- Jan 26, 2018(actual)
Against the original forecast
- Construction start8 weeks earlyforecast May 1, 2017