Wastewater Collection System
Federal contribution
$2.0M
$2,011,168
Federal share48%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2019
201920202021
Built
Approved 11 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of West St. Paul
- Construction start
- Sep 9, 2019(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 6, 2019
- Construction end2 months lateforecast Oct 31, 2020
Also in West St. Paul