Back to projects

Wastewater Collection System

West St. Paul, Manitoba

completeWastewaterCWWF
Federal contribution
$2.0M
$2,011,168
Federal share48%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
201920202021
Built

Approved 11 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 9, 2019(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 6, 2019
  • Construction end2 months lateforecast Oct 31, 2020

Also in West St. Paul

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52157 in the federal list. How to read these figures.