Upgrading of the Ritchance Municipal Bridge
Federal contribution
$79,167
Federal share33%
of $237.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Champlain
- Construction start
- May 1, 2006(actual)
- Construction end
- Jun 19, 2008(actual)
Against the original forecast
- Construction end19 months lateforecast Nov 30, 2006