L'Orignal Standpipe Rehabilitation

Champlain, Ontario

completeDrinking WaterGIS
Federal contribution
$740,000
Federal share54%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Champlain
Construction start
Mar 11, 2024(actual)
Construction end
Dec 2, 2024(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 6, 2024
  • Construction end2 weeks lateforecast Nov 15, 2024