Upgrade to Radio Communications for Water and Sewage Facilities

Champlain, Ontario

completeDrinking WaterCWWF
Federal contribution
$94,105
Federal share48%

of $195.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Champlain
Construction start
Jul 7, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 2, 2017
  • Construction end5 months lateforecast Jan 31, 2019