Riverflow Cycling Trail

Champlain, Ontario

completeRecreationISF
Federal contribution
$1.5M
$1,453,333
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 16, 2009(actual)
Construction end
Nov 19, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2009
  • Construction end4 weeks earlyforecast Dec 15, 2010