King St. Combined Sewer Separation
Federal contribution
$1.2M
$1,223,532
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2020
2021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Champlain
- Construction start
- May 13, 2022(actual)
- Construction end
- Jun 28, 2024(actual)