Replacement of Bridge 29 (Barnstable Bridge)

Milton, Ontario

completeHighways and RoadsMRIF
Federal contribution
$726,400
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Milton
Construction start
Apr 20, 2006(actual)
Construction end
Nov 21, 2008(actual)

Against the original forecast

  • Construction start17 months lateforecast Dec 1, 2004
  • Construction end16 months earlyforecast Mar 31, 2010

Also in Milton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13806 in the federal list. How to read these figures.