Replacement of Four Culverts

King, Ontario

completeHighways and RoadsMRIF
Federal contribution
$476,333
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of King
Construction start
Apr 20, 2006(actual)
Construction end
Sep 19, 2008(actual)

Against the original forecast

  • Construction start4 months lateforecast Dec 31, 2005
  • Construction end18 months earlyforecast Mar 31, 2010

Also in King