Township Wide-Recreation Centre (TWRC)

King, Ontario

completeRecreationCCRIS
Federal contribution
$21.2M
$21,191,377
Federal share40%

of $53.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2021
2022202320242025
Built

Approved 5 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of King
Construction start
Jun 28, 2022(actual)
Construction end
Nov 11, 2024(actual)

Against the original forecast

  • Construction start11 months lateforecast Aug 1, 2021

Also in King

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57584 in the federal list. How to read these figures.