Nobleton-Phase 2 Sanitary Sewer (Contract 1)

King, Ontario

completeWastewaterCWWF
Federal contribution
$248,470
Federal share9%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2017201820192020
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of King
Construction start
Jan 1, 2017(actual)
Construction end
Jun 30, 2020(actual)

Against the original forecast

  • Construction end9 months lateforecast Sep 30, 2019