Back to projects

Construction of a new Schomberg Arena

King, Ontario

completeRecreationISF
Federal contribution
$4.6M
$4,582,426
Federal share31%

of $14.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of King
Construction start
Feb 1, 2010(actual)
Construction end
May 13, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 1, 2009
  • Construction end6 months earlyforecast Oct 31, 2011

Also in King

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31883 in the federal list. How to read these figures.