Construction of a new Schomberg Arena
Federal contribution
$4.6M
$4,582,426
Federal share31%
of $14.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of King
- Construction start
- Feb 1, 2010(actual)
- Construction end
- May 13, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 1, 2009
- Construction end6 months earlyforecast Oct 31, 2011
Also in King
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31883 in the federal list. How to read these figures.