Replacement of Caramat Water Treatment Plant in Greenstone

Greenstone, Ontario

completeDrinking WaterMRIF
Federal contribution
$652,710
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Greenstone
Construction start
Jun 1, 2006(actual)
Construction end
Apr 2, 2008(actual)

Against the original forecast

  • Construction end6 months earlyforecast Sep 30, 2008

Also in Greenstone

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13979 in the federal list. How to read these figures.