Geraldton Ward Main Street Sewer Upgrade
Federal contribution
$220,733
Federal share33%
of $662.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 14, 2015
20162017
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Greenstone
- Construction start
- May 9, 2016(actual)
- Construction end
- Dec 31, 2016(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 9, 2015
- Construction end3 months lateforecast Sep 30, 2016
Also in Greenstone