Rehabilitation of the Longlac Water Treatment Plant

Greenstone, Ontario

underwayDrinking WaterGIS
Federal contribution
$974,160
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
20222023202420252026
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of Greenstone
Construction start
Oct 14, 2024(actual)
Construction end
Aug 14, 2026(forecast)

Also in Greenstone