Geraldton Water Line Rehabilitation Phase II
Federal contribution
$549,923
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
2017
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Greenstone
- Construction start
- Aug 8, 2016(actual)
- Construction end
- Jun 30, 2017(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 30, 2016
Also in Greenstone
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46846 in the federal list. How to read these figures.