Geraldton Water Line Rehabilitation Phase II

Greenstone, Ontario

completeDrinking WaterSCF
Federal contribution
$549,923
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Greenstone
Construction start
Aug 8, 2016(actual)
Construction end
Jun 30, 2017(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 30, 2016