Installation of covered bleachers
Federal contribution
$495,000
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 2, 2006
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Légendes Fantastiques
- Construction start
- Aug 16, 2006(actual)
- Construction end
- Oct 15, 2006(actual)
Also in Drummondville