Wastewater Collection and Treatment Facility
Federal contribution
$2.2M
$2,231,176
Federal share31%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2006
200720082009201020112012
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Pictou
- Construction start
- Jul 27, 2006(actual)
- Construction end
- Jan 3, 2012(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 24, 2005
- Construction end21 months lateforecast Mar 31, 2010
Also in Pictou