New Interceptor Sewer and Water Line Upgrade - East End
Springdale, Newfoundland and Labrador
Federal contribution
$142,097
Federal share33%
of $426.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Springdale
- Construction start
- Apr 11, 2007(actual)
- Construction end
- Oct 16, 2007(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jun 1, 2007
- Construction end6 weeks earlyforecast Nov 30, 2007
Also in Springdale
- Main Street (Hemlock to Little Bay Road) Water, Sanitary Sewer and Storm Sewer Installation and Road Resurfacing$609.5K
- Valley Vista Seniors Home - Emergency Generator Replacement$564.4K
- Water and Sewer Upgrades$428.7K
- Water Line Upgrading$230.5K
- Water & Sewer - Redwood Road to Juniper Road / Sanitary Sewer Outfall$204.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14732 in the federal list. How to read these figures.