R.M. of Strathclair - Lagoon Excavation
Federal contribution
$44,200
Federal share26%
of $168.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2006
2007200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Strathclair
- Construction start
- Dec 19, 2006(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start5 months earlyforecast May 15, 2007
- Construction end4 months lateforecast Aug 31, 2009