Regional Airport Runway Rehabilitation
Federal contribution
$114,067
Federal share33%
of $342.2K total eligible cost; the rest comes from other partners.
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Shoal Lake Airport Authority
- Construction start
- Sep 26, 2017(actual)
- Construction end
- Oct 6, 2017(actual)
Against the original forecast
- Construction end8 months earlyforecast Jun 1, 2018
Also in Yellowhead
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51619 in the federal list. How to read these figures.