Shoal Lake Communiplex Dressing Room Addition

Yellowhead, Manitoba

completeRecreationSCF
Federal contribution
$150,000
Federal share33%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
20182019
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 3, 2018(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2018
  • Construction end2 months lateforecast Dec 19, 2018

Also in Yellowhead

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51643 in the federal list. How to read these figures.