Shoal Lake Communiplex Dressing Room Addition
Federal contribution
$150,000
Federal share33%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Yellowhead
- Construction start
- Jul 3, 2018(actual)
- Construction end
- Feb 28, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2018
- Construction end2 months lateforecast Dec 19, 2018