New Water Treatment Plant Yellowhead
Federal contribution
$2.0M
$2,000,000
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Yellowhead
- Construction start
- May 15, 2017(actual)
- Construction end
- Mar 28, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2017
- Construction end8 months earlyforecast Nov 30, 2018
Also in Yellowhead
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47115 in the federal list. How to read these figures.