New Water Treatment Plant Yellowhead

Yellowhead, Manitoba

completeDrinking WaterCWWF
Federal contribution
$2.0M
$2,000,000
Federal share50%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 15, 2017(actual)
Construction end
Mar 28, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2017
  • Construction end8 months earlyforecast Nov 30, 2018