Water System Improvements Big Pond
Burin, Newfoundland and Labrador
Federal contribution
$235,334
Federal share33%
of $706.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2007
200720082009
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Burin
- Construction start
- Dec 19, 2006(actual)
- Construction end
- Aug 20, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast Sep 1, 2006
- Construction end24 months lateforecast Sep 1, 2007
Also in Burin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14843 in the federal list. How to read these figures.