Water System Improvements – Big Pond

Burin, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$235,334
Federal share33%

of $706.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2007
200720082009
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Burin
Construction start
Dec 19, 2006(actual)
Construction end
Aug 20, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 1, 2006
  • Construction end24 months lateforecast Sep 1, 2007

Also in Burin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14843 in the federal list. How to read these figures.