completeWastewaterSCF
Federal contribution
$159,580
Federal share27%

of $597.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Burin
Construction start
Oct 1, 2016(actual)
Construction end
Nov 16, 2016(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2016
  • Construction end4 months earlyforecast Apr 1, 2017