Back to projects

Town of Burin - Big Pond Chlorination and Water System Improvements

Burin, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$408,122
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020202120222023
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Burin
Construction start
Mar 13, 2020(actual)
Construction end
Aug 30, 2023(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 1, 2020
  • Construction end7 months lateforecast Jan 15, 2023

Also in Burin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53911 in the federal list. How to read these figures.