Town of Burin - Big Pond Chlorination and Water System Improvements
Burin, Newfoundland and Labrador
Federal contribution
$408,122
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Burin
- Construction start
- Mar 13, 2020(actual)
- Construction end
- Aug 30, 2023(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Apr 1, 2020
- Construction end7 months lateforecast Jan 15, 2023