Port au Bras - Water System Improvements

Burin, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$252,601
Federal share40%

of $631.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022202320242025
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Burin
Construction start
Jul 30, 2024(actual)
Construction end
Jul 17, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast May 15, 2024
  • Construction end7 months lateforecast Dec 1, 2024

Also in Burin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61167 in the federal list. How to read these figures.