West Valley Road Reconstruction
Corner Brook, Newfoundland and Labrador
Federal contribution
$1.2M
$1,197,876
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Corner Brook
- Construction start
- Jun 30, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Aug 8, 2009
- Construction end6 months earlyforecast Jun 1, 2011
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14850 in the federal list. How to read these figures.