Mount Bernard Avenue Reconstruction

Corner Brook, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$4.6M
$4,591,409
Federal share40%

of $11.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Corner Brook
Construction start
Sep 23, 2022(actual)
Construction end
Jun 14, 2025(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2022