Trans-Canada Highway from Corner Brook Stream to Pinchgut Lake
Corner Brook, Newfoundland and Labrador
Federal contribution
$3.0M
$3,000,000
Federal share50%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 30, 2010
20102011201220132014
Built
Approved 8 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Newfoundland and Labrador
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Nov 1, 2013(actual)
Against the original forecast
- Construction end5 weeks lateforecast Sep 30, 2013
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36656 in the federal list. How to read these figures.