Back to projects

Recreational Center at Grenfell (Marina Redmond Centre )

Corner Brook, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$7.2M
$7,160,852
Federal share33%

of $21.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 29, 2020
20212022202320242025
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Corner Brook
Construction start
Mar 21, 2022(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 1, 2022
  • Construction end4 months earlyforecast Jun 30, 2025