Divided Highway, Massey Dr. to Corner Brook Industrial Access Road
Corner Brook, Newfoundland and Labrador
Federal contribution
$5.4M
$5,400,000
Federal share50%
of $10.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 30, 2010
2010201120122013
Built
Approved 8 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Newfoundland and Labrador
- Construction start
- Nov 22, 2010(actual)
- Construction end
- Aug 31, 2013(actual)
Against the original forecast
- Construction end11 months earlyforecast Jul 31, 2014
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36650 in the federal list. How to read these figures.