Water Supply Improvements
Port au Port West-Aguathuna-Felix Cove, Newfoundland and Labrador
Federal contribution
$164,063
Federal share33%
of $492.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 25, 2006
2007200820092010
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Port Au Port West-Aguathuna-Felix Cove
- Construction start
- Oct 11, 2006(actual)
- Construction end
- Apr 5, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 1, 2006
- Construction end3 years lateforecast Mar 31, 2007