Waterline Replacement - Phase 4

Port au Port West-Aguathuna-Felix Cove, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$40,237
Federal share27%

of $151.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 10, 2018(actual)
Construction end
Oct 2, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 6, 2018